ARDOT Hwy 70 Widening from I-30 to Hot Springs
$78 million widening 17 miles of US Highway 70 to 5 lanes.
Clearing and grubbing (200 acres), earthwork (1 million cubic yards), aggregate base course (400,000 tons), asphalt paving (300,000 tons), bridges (4), major and minor drainage structures.
Critical Path Scheduling – Completed on time.
Managed 16 subcontractors on the job performing erosion control, striping, rumble strips, major drainage structures, hauling, asphalt and bridges.